Layout Requirements For Standard Single-Row Aisle Containment - Huawei FusionModule2000 Installation Manual

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide
Figure 3-1 Using a laser locator for positioning (dual-row aisle containment)
(1) Marking-off template
Step 4 Use a measuring tape to measure the aisle distance and mark the position for the end cabinet
in the other row in the same way.
----End
3.2 Layout Requirements for Standard Single-Row Aisle
Containment
Prerequisites
The floor levelness meets engineering requirements (levelness tolerance: ± 3 mm).
Preparations
Tools: laser locator, marker, measuring tape
Document: onsite engineering layout diagram
Procedure
Step 1 Determine the installation position for the smart module based on the onsite engineering
layout diagram.
Issue 02 (2018-03-31)
(2) Aisle containment
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Smart Module Layout Requirements
(3) Laser locator
25