FusionModule2000 Smart Modular Data Center
Installation Guide

17.2 Cable Connection Process

Preparations
Tools: thin rope, protective gloves, measuring tape
Materials: cable, marker, label
Procedure
Step 1 Use a thin rope to measure the required cable length based on the actual cable route.
Step 2 Route cables.
1.
2.
Issue 02 (2018-03-31)
Figure 17-8 Direction for securing cable ties
To improve installation efficiency, complete all cable measurements before performing subsequent
operations.
You are advised to lay out cables to the measured cable route length plus about 1 m.
Select the designed cables.
Lay out cables to the required length.