FusionModule2000 Smart Modular Data Center
Installation Guide
Figure 10-27 Installing the dampers
1.
2.
3.
4.
Step 4 Install the hanging kits and door boxes, as shown in
For cabinets with different depths, the number of conversion brackets to be installed may differ, but the
installation method is the same. The following uses a 1200 mm deep cabinet as an example to describe
how to install conversion brackets.
Figure 10-28 Installing the hanging kits and door boxes
1.
Issue 02 (2018-03-31)
Slide a damper into the glass door, as shown by (1) in
Snap the damper into the post, and verify that the damper is in close contact with the post,
as shown by (2) and (3) in
Secure the damper to the post using two M4x10 countersunk screws, as shown by (4) in
Figure
10-27.
Install the damper on the other side in the same way.
Snap the middle door box into the upper frame mounting kit. Secure the middle door box
to the door frame using three M4x12 screw assemblies, as shown by (1) in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
10-27.
Figure
10 Installing the Aisle Containment
Figure
10-27.
10-28.
Figure
10-28.