FusionModule2000 Smart Modular Data Center
Installation Guide
To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the No. 0 packing
box.
2.
3.
(1) Column
Step 7 Install PC plates.
1.
2.
Issue 02 (2018-03-31)
Use a marker to mark a line on the column where the PC plate closely attaches to the
column.
Move away the PC plate. Drill holes in the column and secure the L-shaped mounting
brackets to the column using plastic expansion bolts.
Figure 10-12 Securing L-shaped mounting brackets
Pave the PC plate on the adjustable skylight.
Secure PC plate fasteners to PC plate supports.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Installing the Aisle Containment
104