FusionModule2000 Smart Modular Data Center
Installation Guide
Do not remove the anchor bolts. Otherwise, rework is required if the cabinet height does
not meet requirements.
Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet, or
wrench an anchor bolt anticlockwise to lower it. Anchor bolts can be adjusted within a
range of 0–8 mm.
Put a level at the bottom of the cabinet in width and depth directions and check that the air
bubble is in the middle between the two lines marked on the glass tube.
Figure 8-2 Leveling a cabinet
(1) Level
Step 3 (Optional) Secure cabinets on the bases.
Perform this step if bases are required.
Issue 02 (2018-03-31)
For the PDC, network cabinet, IT cabinet, 600 mm wide air conditioner, and 300 mm
wide M-type air conditioner:
a.
Install the spring washers, flat washers, and insulation coverings on the bolts.
b.
Use an M20 torque wrench to tighten the four bolts in diagonal order.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Combining Cabinets
85