FusionModule2000 Smart Modular Data Center
Installation Guide
Preparations
Tool: Phillips screwdriver
Materials: cable trough and accessories
Document: cable trough installation position diagram
Procedure
Step 1 Keep a vertical plate of the cable trough flush with the top surface of the cabinet and clamp
the clasps into the mounting holes in the first row counting from the front door to the rear
door.
Figure 11-3 Clamping a vertical plate
Step 2 Rotate the vertical plate by 90 degrees to stand it on the top plate of the cabinet.
Figure 11-4 Rotating the vertical plate by 90 degrees