Huawei FusionModule2000 Installation Manual page 292

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide
6.
7.
Issue 02 (2018-03-31)
Figure 17-21 Connecting power cables to the circuit breaker
(Optional) If the intelligent battery monitoring system is not deployed, use a 04080376
cable to connect the J1 port on the battery control board (BIB) to the corresponding port
on the UPS. Alternatively, use a 04080377 cable for cascading and use a 04080376 cable
for connecting to the corresponding port on the UPS.
Figure 17-22 Connecting monitoring cables to the circuit breaker
(Optional) If an intelligent battery monitoring system is installed, see iBAT
2.0-CIM01C2 User Manual for details about the installation, cable connection, and
power-on of the BIM and CIM.