Optional) Installing A Vcn500 - Huawei FusionModule2000 Installation Manual

Smart modular data center
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide
Step 4 Connect the server power cables to the rPDU.
Figure 15-5 Connecting server power cables
----End

15.1.2 (Optional) Installing a VCN500

Preparations
Tool: Phillips screwdriver
Material: VCN500
Document: installation position diagram for monitoring devices in the network cabinet
Procedure
Step 1 Determine the mounting holes for a VCN500 based on the installation position diagram for
monitoring devices in the network cabinet, adjust the guide rails, and install floating nuts.
Issue 02 (2018-03-31)
The server uses dual power supplies. Connect the two power cables to different rPDUs.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
15 Installing Monitoring Devices
182