FusionModule2000 Smart Modular Data Center
Installation Guide
Preparations
Tools: Phillips screwdriver, handsaw, flat-head screwdriver, wire stripper, crimping tool
Materials: dehumidifier and accessories, PVC glue, AB glue, cord end terminal, OT terminal,
brush, sealing tape
Procedure
Step 1 Find the air conditioner located in the middle of the aisle, and move the dehumidifier to the
bottom of the IT cabinet adjacent to this air conditioner.
Step 2 Secure the tray to the rack rail at 1 U height at the bottom of the cabinet using M6 screws.
Figure 13-2 Installing a tray
Step 3 Place the dehumidifier on the tray and move it to its installation place, and install floating nuts
at the mounting holes for dehumidifier mounting ears.
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
13 (Optional) Installing Dehumidifiers
172