FusionModule2000 Smart Modular Data Center
Installation Guide
Press down the stop block springs when installing the stop block screws.
Step 3 Install dampers, as shown in
1.
2.
3.
4.
Issue 02 (2018-03-31)
Figure 10-35 Installing the guide rail and glass doors
Slide a damper into the glass door, as shown by (1) in
Snap the damper into the post, and verify that the damper is in close contact with the post,
as shown by (2) and (3) in
Secure the damper to the post using two M4x10 countersunk screws, as shown by (4) in
Figure
10-36.
Install the damper on the other side in the same way.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
10-36.
Figure
10-36.
10 Installing the Aisle Containment
Figure
10-36.
126

Advertisement

Table of Contents
loading

Table of Contents