Procedure
Step 1 Open the cabinet rear door and use four M4 screws to secure the vertical ground bar to the
right mounting bar.
Figure 6-8 Installing a vertical ground bar
----End
6.9 (Optional) Setting a Cabinet Code Lock
Context
Issue 02 (2018-03-31)
The specific securing positions are the screw holes in the middle of the 04 U, 14 U, 29 U, and 39 U
positions.
The cabinet code lock can be unlocked with a key or password. If you do not need the
password function, you can use a key to unlock the cabinet.
The preset password for the cabinet code lock is 0, 0, 0.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 Installing the Network Cabinet, IT Cabinet, and Battery
Cabinet