9.1 Commissioning Power Distribution Components

9.1.1 Commissioning the Power Distribution Cabinet

Prerequisites
Preparations
Tool: multimeter
Documents: power supply and distribution system diagram, power supply and
distribution device layout diagram
Skill requirement: power distribution engineer
Procedure
Step 1 Switch on the input power circuit breaker to power on the PDF.
1.
2.
Issue 03 (2022-12-15)

Commissioning Core Components

You have verified all the specifications for the power-on.
You have put on protective articles.
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
NO TE
● The input power circuit breaker refers to the output circuit breaker that controls power
supply from the upstream power distribution equipment to the PDF.
● If the power indicators (if configured) on the PDF have turned on, the PDF has been
powered on.
● The general PDF circuit breaker can be an ATS, MCCB, or MCB.
(Optional) If an ATS is configured, go to
(Optional) If an MCCB or MCB is configured, go to