8-6-2-7
Calibration and adjustments
Refer to:
8-6-2-8
Verification
Perform the following steps to verify that the product is functioning as intended after this replacement:
1.) Verify that all screws that you removed earlier have been installed.
2.) If finished, connect cables and Probes removed earlier.
3.) Power up the system to verify that it operates as intended.
8-6-2-9
Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
If all are successful, include the following debrief script: LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Equipment passed all required checks and is ready for use.
See:
Section
4-2-2
4-2-3
4-3-5
4-3-7
6-3-4
. 2
EV
Section 6-3 "LCD Monitor adjustments" on page 6-2
Table 8-62
LCD Monitor assembly replacement Functional Checks
Functional Check
Power ON/Boot Up
Power shut down
B-Mode Checks
System CFM and PWD Checks
LCD Adjustment Procedure
Chapter 8 Replacement procedures
for LCD Monitor calibration instructions.
Debrief Script
LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Leakage Current
measured at (record the value) and meets
allowable limits. Equipment passed all required
checks and is ready for use.
LOGIQ E9 S
M
ERVICE
ANUAL
8 - 101