8-5-12
Door, I/O Panel replacement
8-5-12-1
Manpower
One person, 15 minutes.
8-5-12-2
Tools
For tools needed, refer to:
8-5-12-3
Preparations
When preparing for the replacement, you must perform the following steps:
1.) Power down the system
2.) Disconnect the mains power cable from the wall outlet.
Follow this link if you need more information:
4-2-3 "Power shut down" on page 4-7.