 Mount point change of installation frame from the rear to the front
The upper and lower installation frames are attached on the inverter (one for each position).
Change the mount point of the upper and lower installation frames from the rear to the front as shown in the figure.
When reattaching the installation frames, make sure that the installation orientation is correct.
 Installation of the inverter on the enclosure
Push the inverter heat sink part outside the enclosure, and fix the inverter to the panel with upper and lower installation frames.
NOTE
• As the heat sink part protruded through the panel includes a cooling fan, this type of installation is not suitable for the
environment of water drops, oil, mist, dust, etc.
• Be careful not to drop screws, dust etc. into the inverter and cooling fan section.
Downloaded from
ManualsNet.com
Shift
Shift
Inside the
Exhausted air
enclosure
Inverter
Cooling
wind
185 mm
search engine
Upper
installation
frame
Lower
installation
frame
Enclosure
There are finger guards behind the enclosure.
Therefore, the thickness of the panel should be
*1
less than 10 mm (
) and also do not place
anything around finger guards to avoid contact
with the finger guards.
Enclosure
Installation
frame
*1
140 mm
10 mm
Dimension of
the outside of
the enclosure
Finger guard
2. INSTALLATION AND WIRING
2.3 Installation of the inverter and enclosure design
1
2
3
4
5
6
7
8
9
10
45

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents