Installing Panels
1.
2.
Figure 10-31 Installing filler panels
10.9.2 Connecting Cables to Power Supply and Distribution
Devices
To connect cables to power supply and distribution devices, see the documents delivered with
the devices. Table 10-3 lists the reference documents.
Table 10-3 Reference documents for power supply and distribution devices
Device Name
(Optional) Industrial
connector cable
connection
(Optional) PDU2000
cable connection
Integrated PDC
Integrated UPS
Issue 04 (2017-06-30)
Reinstall the circuit breaker panel.
Secure filler panels to the rack rails on the rear door, as shown in Figure 10-31.
Each filler panel occupies 2 U. Install them according to the U position markings on the cabinet. Ensure
that filler panels fully cover the rack rails.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Reference
A.6 (Optional) Connecting Cables to Industrial Connectors
A.7 (Optional) Connecting PDU2000 Cables
PDU8000 Integrated Power Distribution Cabinet Quick Guide
(Modular)
The document is delivered with the device, or you can click
Download.
UPS5000-E-(40 kVA–128 kVA) Quick Guide (Integrated UPS
2.0)
The document is delivered with the device, or you can click
Download.
10 Cable Routing
201

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents