Figure 4-12 Drainpipe routed from the bottom
● After routing the water pipe, secure it to the pipe assembly using cable ties,
and seal the cable hole using firestop putty.
● After connecting the drainpipe, check whether the drainage is normal.
Step 4 Install the baffle plate for the smart cooling product.
----End
Follow-up Procedure
Before removing the smart cooling product, remove the upper baffle plate and the
side panels on both sides of the cabinet.

4.2.5 Installing Power Supply and Distribution Devices

4.2.5.1 Installing Lithium Batteries

Context
Install lithium batteries in the 11th U and higher positions of the cabinet.
Procedure
Step 1 Push a lithium battery into the cabinet and secure it.
Issue 02 (2021-06-30)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
68