Figure 7-36 Installing the mounting plate of the magnetic lock cover
Step 6 Install the magnet.
1.
2.
When securing the magnetic to the door panel, do not over-tighten the screws so that the white rubber
washer is elastic. The washer will adjust the magnetic to a correct position because of its elasticity.
Issue 04 (2017-06-30)
Take out the magnet from the magnetic lock fitting bag, and knock the positioning pins
of the magnetic into the magnet using a rubber mallet.
Figure 7-37 Installing positioning pins of the magnetic
Insert the assembled magnet into the magnetic lock base on the revolving door, and
secure the magnet to the door using the screws on the door and the white washer
delivered with the magnet lock.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Installing Monitoring Devices
146

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents