Figure 3-50 Leveling a base
Step 4 If a base is not level, put spacers under it, as shown by (2) in Figure 3-50.
Step 5 Tighten expansion bolts, as shown by (3) in Figure 3-50.
Step 6 Secure other bases in the same way.
Step 7 Connect bases using connecting plates, as shown by (1) in Figure 3-51.
Figure 3-51 Connecting bases
Step 8 Screw the floor holder to the base, as shown by (2) in Figure 3-51.