Laying Out The Water Detection Cable (Top Pipe Routing) - Huawei FusionModule2000 Installation Manual

Smart modular data center, 2000 mm high cabinets, single-row aisle containment, 380 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)

7.13.2 Laying Out the Water Detection Cable (Top Pipe Routing)

Context
Figure 7-71 Laying out a water detection cable (top pipe routing)
(1) ECC800
Do not contact the water detection cable to metal, for this action will cause a false alarm. Take
protective measures when routing a water detection cable.
Procedure
Step 1 Plan the installation position for the fastener of the water detection cable. Ensure that the
water detection cable placed on the fastener is in good contact with the floor.
Step 2 Tear off the protection paper from the rear of the fastener, and then securely attach the
fastener to the floor.
Issue 04 (2017-06-30)
(2) Network cable
One fastener is provided for a 1 meter long water detection cable.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Installing Monitoring Devices
(3) Water detector
(4) Water detection cable
172