Correct Method for Connecting Battery Cables
Issue 04 (2017-06-30)
Figure 10-24 Attaching the battery label
Route and secure cables between layers along the rack rail in the vertical direction, as
shown by (1) in Figure 10-25.
Route and secure cables between layers along the tray supporting beam in the horizontal
direction, as shown by (2) in Figure 10-25.
Figure 10-25 Cable routes
(Optional) When battery cabinets are installed adjacent to each other, remove the upper
side plates from the battery cabinets for routing cables to the corresponding ports.
When the length of a battery cable equals the distance between two battery terminals,
connect the cable straight through, as shown in Figure 10-26.