Huawei FusionModule2000 Installation Manual page 71

Smart modular data center, 2000 mm high cabinets, single-row aisle containment, 380 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Figure 3-47 Positioning the first base
Step 5 Use the end cabinet base as the reference and place other cabinet bases.
Step 6 Check that L1, L2, L3, and L4 meet the following requirements: |L1–L2| ≤ 5 mm and |L3–L4|
≤ 5 mm.
Figure 3-48 Base layout (unit: mm)
Step 7 Use a marker to mark hole positions.
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.