Figure 6-2 PDU2000 cable routing on the top of a cabinet
(1) Weak-current cable trough
Procedure
Step 1 Keep a vertical plate of the cable trough flush with the top surface of the cabinet and clamp
the clasps into the mounting holes in the first row counting from the front door to the rear
door.
Figure 6-3 Clamping a vertical plate
Step 2 Rotate the vertical plate by 90 degrees to stand it on the top plate of the cabinet.
Issue 04 (2017-06-30)
The trough for routing strong-current cables must be close to the contained aisle.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 (Optional) Installing Cable Troughs
(2) Strong-current cable trough