FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Figure 3-49 Positioning holes
----End
3.8.2.1.3 Securing Bases
Prerequisites
The base has been positioned.
Procedure
Step 1 Move the base, and drill holes to depths of 52 mm to 60 mm using a hammer drill with a Φ16
drill bit.
Step 2 Move back the base, and partially tighten the expansion bolts.
Step 3 Measure the levelness of the base using a level, as shown by (1) in Figure 3-50.