Step 3 Connect the wiring terminal to the high float cable, and place the wiring terminal above the
water tank to avoid wetting in the case of water overflow.
The wiring terminals must stay in good contact with the floats. Otherwise, the condensate
pump cannot start properly.
Figure 3-10 Removing the transport fasteners from the floats and connecting the wiring terminals
----End
3.1.2.9 Removing the Transport Fasteners from a Compressor
Context
When removing transport fasteners, do not remove the fuel return solenoid valve. Otherwise,
the solenoid valve might be burnt due to improper reinstallation.
Procedure
Step 1 Loosen the three bolts on a compressor using a 13# solid wrench, as shown in Figure 3-11.
Step 2 Remove the transport fasteners.
Issue 04 (2017-06-30)
The wiring terminal to the low float has been factory installed.
Store the removed fasteners. They should be reinstalled and the wiring terminal should be
disconnected from the high float cable if the equipment needs to be transported in future.
Do not directly take the bolts out.