Figure 7-34 Removing the fixing plate of a magnetic lock
Step 3 Install the magnetic lock fixing plate. Secure the magnetic lock fixing plate to the upper frame
mounting kit using eight M4 countersunk screws, as shown by (1) in Figure 7-35.
Pay attention to the direction of the magnetic lock fixing plate, and ensure that the protruded
surface of the magnetic lock faces the magnet.
Step 4 Install the magnetic lock. Route cables of the magnetic lock into the upper frame mounting kit,
and secure the magnetic lock to the fixing plate using the hex key delivered with the magnetic
lock, as shown by (2) in Figure 7-35.
Figure 7-35 Installing a magnetic lock
Step 5 Install the mounting plate of the magnetic lock cover.
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Installing Monitoring Devices
145

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents