1.
To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the No. 0 packing
box.
2.
3.
(1) Column
Step 4 Install PC plates.
1.
2.
Issue 04 (2017-06-30)
Trim the PC plate using a hook knife and place it on the adjustable skylight.
Mark a line on the column where the PC plate closely attaches to the column using a
marker.
Move the PC plate. Drill holes on the column and secure the L-shaped mounting
brackets to the column using plastic expansion bolts.
Figure A-24 Securing L-shaped mounting brackets
Pave PC plates on the adjustable skylight.
Secure PC plate clips to PC plate supports.