Sealing Plate
600 mm wide, 2000 mm high sealing plate
800 mm wide, 2000 mm high sealing plate
300 mm wide, 2200 mm high sealing plate
600 mm wide, 2200 mm high sealing plate
800 mm wide, 2200 mm high sealing plate
Procedure
Step 1 Determine the positions of sealing plates, directions of the concave sides of sealing plates, and
the area covered by the adjustable skylight based on the actual installation environment.
Step 2 Install the sealing plates near the aisle.
1.
2.
3.
Issue 04 (2017-06-30)
Install the sealing plates near the aisle containment first, and then the sealing plates near the smart
module exterior.
Secure the two sealing plates using three M6 screws and nuts.
Place the connected sealing plates at the specified installation position, facing the correct
direction.
Use a hammer drill with a 15 mm drill bit to drill four holes that are 45–50 mm deep at
the bottom of the sealing plate, and secure the sealing plate to the floor using four plastic
expansion bolts (labeled DKBA44091028) and washers.
If drilling holes in the ESD floor is not allowed onsite, use four ST4.8x25 self-drilling tapping screws
and washers for securing.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
BOM Number
21500718
21500720
21500939
21500940
21500941
A Appendix
217

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents