Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
Operations marked as optional in chapters, sections, or procedures can be performed depending on the actual situation. Huawei assumes no liability for any loss caused by unauthorized changes to the initial configuration parameters. Issue 02 (2017-01-10) Huawei Proprietary and Confidential...
Step 4 Check that the views and videos in the management system are consistent with the running status of the data center. For details, see NetEco Commissioning Guide and NetEco Administrator Guide. If any inconsistency is found, contact Huawei technical support. ----End 7.4 Commissioning the Fire Extinguishing System...
Step 1 Verify configurations of the PD510 electricity meter by referring to the delivered documents. During the PD510 electricity meter power-on commissioning, you are not allowed to modify the initial configurations unless you are authorized by onsite Huawei engineers. Step 2 Set a protection password for the PD510 electricity meter.
Page 82
During the MDU power-on commissioning, you are not allowed to modify the MDU initial configurations unless you are authorized by onsite Huawei engineers. Step 3 Enter a user name and password to access the MDU, set the user name, password, time, and language, and check that the initial parameter settings are correct.
During the power-on commissioning, you are not allowed to switch on the bypass circuit breaker for the UPS5000-E. During the power-on commissioning, you are not allowed to modify the UPS5000-E initial configurations if not authorized by Huawei onsite engineers. For the setting method, see the UPS5000-E user manual. ...
During the UPS2000-G power-on commissioning, you are not allowed to modify the UPS2000-G initial configurations unless you are authorized by onsite Huawei engineers. Step 3 Enter the user name and password to enter the operation screen, and verify that initial parameter settings are consistent with the initial configuration table.
When powering on and commissioning the 30 kW chilled water precision air conditioner, you are not allowed to modify the initial configurations of the 30 kW chilled water precision air conditioner unless you are authorized by onsite Huawei engineers. ...