Check Item
Power supply
Equipment room fire
extinguishing
Floor drain
Module grounding
Monitoring port
If any of the requirements is not met, contact Huawei technical support.
Issue 04 (2017-06-30)
Requirement
380–415 V AC, 3-phase, 50/60 Hz
Indoor gaseous fire extinguisher
DN50 or larger, made of cast iron or
stainless steel
The equipment room grounding
system must be a TN-S or TN-C-S
system.
The equipment room ground grid
must have a ground resistance of 10
ohms at most (If the ground
resistance exceeds 10 ohms, ensure
that the equivalent ground radius of
the ground grid exceeds 5 m.)
Ground bars must be deployed over
the cable tray or under the raised
floor
One LAN switch Ethernet port:
connects to the customer subnet to
monitor devices inside the module.
(Optional) Two fire control dry
contacts (access actuator and PDC
fire control terminal): connect to the
fire extinguishing system of the
equipment room for interaction.
(Optional) SIM card: supports 3G
(WCDMA) communication and is
compatible with 2G (GSM)
communication. If the collector
supports the SMS alarm function,
configure a SIM card.
NOTE
If there are multiple modules, configure a
collector for each module. For the collectors
that support the SMS alarm function,
configure a SIM card for each.
IP address: Each collector, camera,
and VCN require an IP address,
respectively.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1 Installation Preparations
Check Result
□ Compliant □
Incompliant
□ Compliant □
Incompliant
□ Compliant □
Incompliant
□ Compliant □
Incompliant
□ Compliant □
Incompliant