Hoisting And Securing Pre-Fab. Modules - Huawei FusionModule1000A40 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One
Data Center
Installation Guide

5.2.3 Hoisting and Securing Pre-fab. Modules

Prerequisites
To facilitate subsequent installation, ensure that pre-fab. modules are level after
hoisting.
Context
Ensure that the crane and steel ropes can bear the load weight.
Table 5-3 Parameters for hoisting pre-fab. modules
Weight
Net weight: <
14,000 kg
Hoisting Precautions
Stage
Before hoisting
During hoisting
Issue 07 (2022-12-15)
NO TICE
Pre-fab. module bases have been installed and leveled.
Select an appropriate crane based on standards of the crane company, and
ask a professional to assess the crane onsite.
Twistlocks in pre-fab. module bases are in correct positions.
The hoisting ropes are available.
The doors of pre-fab. modules to be hoisted are closed.
The weather is good without wind when pre-fab. modules need to be hoisted
outdoors.
Steel
Rope
Length
> 12.5 m
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
Ensure that the twistlocks in container bases are in correct
positions.
Ensure that the steel ropes are securely connected.
Do not allow any unauthorized people to enter the
hazardous areas and never stand under the crane arm
during hoisting.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Steel Rope
Dimensions (H x W x D)
Quantity
4 PCS
2896 mm x 2438 mm x 12192 mm
5 Installing Pre-fab. Modules
51