Optional) Base Installation Scenario; Installing Pre-Fab. Module Bases - Huawei FusionModule1000A20 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Follow-up Procedure
After pre-fab. modules are hoisted and installed, verify the installation to ensure normal use of
products and smooth subsequent installation.
Table 4-2 Installation checklist
No.
1
2
3

4.2 (Optional) Base Installation Scenario

4.2.1 Installing Pre-fab. Module Bases

Prerequisites
Concrete platform levelness is critical to pre-fab. module installation. Ensure that the concrete
platform meet requirements before installing pre-fab. module bases.
Context
Before installing pre-fab. modules, determine their installation positions and directions based
on site space.
Issue 02 (2020-01-15)
Check Item
Contact between pre-fab.
modules and concrete
platforms
Bolts and nuts
Pre-fab. module doors
The field meets site requirements.
Before installing pre-fab. modules, check the height of concrete platforms and ensure
that the height (altitude) error between the upper surfaces of all platforms does not
exceed 5 mm.
Copyright © Huawei Technologies Co., Ltd.
Check Method
Observe.
Partially tighten them
using a wrench.
Open and close each
pre-fab. module door
once.
4 Installing Pre-fab. Modules
Criteria
A pre-fab. module is in
close contact with and
evenly supported by the
concrete platforms.
Bolts and nuts are
tightened.
All pre-fab. module
doors can be smoothly
opened and closed.
19