ECC800 Data Center Controller
User Manual
Feature Description
The linkage control configuration is concise and easy to operate. You can perform the
following operations:
The following are descriptions of the WebUI:

9.2 Linkage Control Configuration Examples

Context
Procedure
Step 1 Log in to the ECC800 WebUI as an administrator.
Step 2 Choose System Settings > Linkage Control.
Step 3 Ensure that Enable linkage control function is Yes.
Step 4 Add or edit a linkage group name.
Issue 05 (2019-09-16)
Configure linkage control logic programs on the WebUI for display.
Import or export configuration files.
Restore the default linkage control configuration by one click.
Basic Parameters: The configurations of the linkage control logic programs are valid if
Enable linkage control function is set to Yes.
Linkage group: You can configure Linkage groups by type.
Linkage Logical List: You can configure logic program lines.
Import and Export: You can import or export configuration files to generate logic
program lines in batches.
Restore configuration: You can click Restore Factory Defaults to restore the default
linkage control configurations.
Linkage control does not need to be configured onsite and its default configuration applies.
Before adding or modifying linkage control linkage logic, consult Huawei engineers.
When you do not know how to rectify the incorrect linkage control configuration or want
to synchronize the linkage control configuration from another ECC800, use the linkage
control configuration import and export function.
The ECC800 supports fire control linkage and high temperature linkage control. For
example, the ECC800 can implement fire linkage by detecting fire alarms through the
fire controller and opening the skylight, opening the aisle door, and shutting down the
smart cooling product based on the alarm status.
The following describes how to configure the linkage control linkage, using Link fire
control with skylight open as an example.
In this example, the fire controller connects to the AI/DI_1 port. The actual port prevails.
Copyright © Huawei Technologies Co., Ltd.