Commissioning of a Redundant System Setup
the front of the CIU 888 (see FIGURE 5-2). See CHAPTER 3 for
more information about the CIU 888 Configuration System.
CIU 888: Service port
During commissioning of the CIU 888s, the Entis Pro system(s)
connected to the CIU 888s must be shut down.

5.2 Running the initial setup of the primary CIU 888

The first step in the procedure for the commissioning of a redundant
CIU 888 system setup is performing the initial setup procedure of the
primary CIU 888. See section 4.2 for more information.

5.3 Setting up the site configuration

When the initial setup of the primary CIU 888 is completed, then set up
the site configuration using CIU 888 Service Tool. The site configuration
can be set up either by:
Creating a new site configuration, see section 3.2.
or
Importing an existing CIU 888 site configuration, see section 3.6.

5.4 Sending the site configuration to the primary CIU 888

When the site configuration is set up, send the site configuration to the
primary CIU 888 using the CIU 888 Service Tool. See section 3.3 for
more information.
5.5 Commissioning of the secondary CIU 888
When the primary CIU 888 is commissioned, then configure its
counterpart as preferred secondary CIU 888.