Preface

PREFACE

General

Commissioning is the first step after the installation of the CIU 888.
During commissioning, the CIU 888 site configuration is created and
site elements such as CIU, field ports, tanks, GPU data inputs, Modbus
data inputs, TRL/2 data input, and host ports are configured.
When the site is in operation and there are changes, for example a
gauge is added or an additional host system is connected, these
changes need to be implemented, and the CIU 888 needs to be
updated with the new site configuration.

Purpose of this manual

The purpose of this manual is to provide information about the
commissioning and configuration of the CIU 888.For the migration of an
existing CIU 880 Prime/Plus site configuration to the CIU 888, See
chapter 3.2.4 "Ensite pro database import option".

Target audience of this manual

This manual is primarily intended for service technicians who are
responsible for commissioning and configuration of the CIU 888.