Required Tools and Equipment (ETSI)
Only use the power cables that are designed to be used with ONS 15454 ETSI. They are sold separately.
Caution
User-Supplied Equipment (ETSI)
The following materials and tools are required for installation but are not supplied with the
ONS 15454 ETSI:
Note
Ring runs are not provided by Cisco and can hinder side-by-side shelf installation where space is limited.
Tools Needed (ETSI)
To install the ONS 15454 ETSI, you need the following tools.
Test Equipment (ETSI)
To install the ONS 15454 ETSI, you need the following test equipment.
Cisco ONS 15454 DWDM Procedure Guide, Release 9.2
1-6
Equipment rack (ETSI rack, 2200 mm [86.6 inch] H x 600 mm [23.6 inch] W
x 300 mm [11.8 inch] D)
Fuse and alarm panel
Copper ground cable 13.3-mm² (#6 AWG) stranded, specified for up to 90 degrees Celsius
(194 degrees Fahrenheit)
Alarm cable pairs for all alarm connections, 0.51 mm² or 0.64 mm² (#22 or #24 AWG), solid-tinned
Single-mode SC fiber jumpers with UPC polish (55 dB or better) for optical cards
Coaxial cable terminated with 1.0/2.3 miniature coax connectors for FMEC cards
DB-37 cable
Shielded BITS clock coaxial cable terminated with 1.0/2.3 miniature coax connectors
Labels
Wire wrapper
Wire cutters
#2 Phillips Dynamometric screwdriver
Medium slot-head screwdriver
Small slot-head screwdriver
Video fiber connector inspection instrument
CLETOP cleaning cassette
Crimping tool—This tool must be large enough to accommodate the girth of the grounding lug when
you crimp the grounding cable into the lug.
Wire stripping tool
Voltmeter
Power meter (only for use with fiber optics)
Chapter 1
Install the Cisco ONS 15454 Shelf Assembly
78-19286-01

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ons 15454Ons 15454 m2Ons 15454 m6

Table of Contents