Installing Monitoring Devices; Optional) Installing A 2288X V5 Server - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)

8.3 Installing Monitoring Devices

This manual does not cover the installation of upstream monitoring devices. For
the detailed installation methods, see
(NetEco Version) .
If the NetEco is deployed inside the pre-fab. module, it occupies space for server
cabinets. It is recommended that the NetEco be deployed under the ECC800-Pro in
the A1 cabinet. The server, LAN switch, and IVS respectively occupy 2 U, 1 U, and 2
U space.

8.3.1 (Optional) Installing a 2288X V5 Server

Context
Tool: Phillips screwdriver
Material: 2288X V5 server
Procedure
Step 1 Place the server on the guide rails and slide it along the guide rails into the
cabinet.
Step 2 Align the two mounting ears of the server with the mounting bars of the cabinet
and tighten the screws on the mounting ears.
Figure 8-10 Installing a server
Step 3 Connect the server power cables to the PDU2000.
Issue 01 (2021-04-20)
NO TE
The server uses dual power supplies. Connect the two power cables to different PDU2000s.
Copyright © Huawei Technologies Co., Ltd.
8 Installing Devices Inside the Pre-fab. Module
iManager NetEco Product Document -
75

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents