Step 4 Route the external input power cables into the power PDB through the cable holes
at the bottom, and route them out along the cable bridge above the cable holes.
Figure 9-2 Connecting input power cables for the power PDB
Step 5 Connect the cables by following the instructions in
Techniques.
After connecting the cables, seal the two cable holes at the bottom of the power
PDB using waterproof sealing putty.
Step 6 Reinstall the transparent cable protection panel, and close the door of the power
PDB.
----End
9.2 (Optional) Connecting Generator Start/Stop Cables
(ATS Input)
Procedure
Step 1 Connect the generator start/stop cables to the terminals on the XT2 terminal
block.
Issue 01 (2021-04-20)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
9 Installing Cables Outside the Pre-fab. Module
A.1 Cable Installation
98

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents