FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 4-7 Base installation scenario diagram (unit: mm)
(1) Pre-fab. module base
Step 2 Determine the installation position for the first base in the installation area based
on the site space, and draw longitude and latitude reference lines between the
first base and other bases.
● Lines should be perpendicular or parallel, with an angle of 90 degrees at cross
points.
● The point where the reference lines intersect is the middle point for installing a
pre-fab. module base.
Step 3 Place bases based on the reference lines.
Issue 01 (2021-04-20)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
(2) Concrete platform
4 Installing a Pre-fab. Module
(3) Ground