Figure 6-2 Installing pipes
(1) Water refill pipe
1.
2.
3.
Step 4 After the hot-melt connection, wrap the exposed part of the water pipe with 10
mm thick thermal insulation foam.
----End
Follow-up Procedure
Verify that the pipe connector is closely melted with the pipes at both ends.
Issue 01 (2021-04-20)
Remove the tinfoil on the plug of the water refill valve.
Connect the PP-R pipe connector to the pipes on both ends using a hot melt
device.
Install the other pipes in the same way.