Huawei FusionDC1000A Installation Manual page 81

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 8-8 Secure the temperature probe
Step 4 Connect the electric heating belt and temperature probe to the controller.
Figure 8-9 Wiring diagram
Step 5 Install thermal insulation foam on pipes.
----End
Issue 01 (2021-04-20)
NO TE
Wrap the electric heating belt before wrapping the thermal insulation foam, and the
thermal insulation foam covers the electric heating belt. Verify that the thermal insulation
foam can withstand a temperature greater than or equal to 200°C.
Copyright © Huawei Technologies Co., Ltd.
8 Installing Devices Inside the Pre-fab. Module
74

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents