A.1 Cable Installation Techniques
A.1.1 Cabling Rules
Cable Layout
When laying out cables, observe the following rules:
Binding Cables
When binding cables, observe the following rules:
Issue 01 (2021-04-20)
A
Basic Installation Operations
Determine the cable specifications, route, cross-sectional area, and location
according to the construction drawings.
Cables must be neatly arranged and cable insulation layers must be intact.
Different types of cables must be routed separately.
Connection ports and cabling methods must facilitate maintenance, cable
routing, and capacity expansion.
Cable connectors prepared onsite must be secure, reliable, and neat, and
conform to specifications.
Power cables, ground cables, and signal cables must be securely connected.
Adapters must be securely plugged or screwed.
Power cables and signal cables must be bound separately.
Bind cables with a proper strength and do not pull the cables during binding.
The labels on both sides of a cable must be concise, easy to understand, and
face outwards.
Cable ties must be neatly cut without sharp burs, evenly distributed, bound to
a proper strength, and fastened towards the same direction, as shown in the
figures.
Cables must be bound closely and neatly. Each bundle must not exceed 15
cables.
Copyright © Huawei Technologies Co., Ltd.