FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
● Longitudinal and latitudinal symmetric lines are stamped on bases in the
factory. When installing bases, verify that the 400 mm edges of the bases are
parallel with the length direction of the pre-fab. module, and that the
symmetrical lines are aligned with the reference lines.
● After placing all the bases, measure the diagonal distances between the four
outermost bases for the pre-fab. module, and ensure that the diagonal length
deviation is within 5 mm.
Step 4 Mark the hole positions for installing pre-fab. module bases on the concrete
platforms using a marker.
Figure 4-8 Determining hole positions for installing a pre-fab. module base
● When marking hole positions for a base, ensure that the symmetric lines on the
base are aligned with the reference lines you marked.
● There are eight mounting holes for one single-capacity base. Mark all the hole
positions.
Step 5 Move away the pre-fab. module bases, and install expansion bolts in the base
mounting holes.
Issue 01 (2021-04-20)
NO TICE
NO TICE
Copyright © Huawei Technologies Co., Ltd.
4 Installing a Pre-fab. Module
39

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents