FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 8-30 Connecting battery cables
----End
8.4.3 (Optional) Connecting the Cables to ASD Power Box
Batteries
Context
The ASD power box and batteries inside the pre-fab. module have been installed
before delivery. You only need to connect the reserved cables to the batteries
onsite.
Preparations
Tool: Phillips screwdriver
Materials: none
Skill requirement: common technician
Procedure
Step 1 Open the power box using a key.
Step 2 Remove the protective foam from the batteries and check whether the batteries
are intact or leak.
If a battery is damaged or leaks, contact Huawei technical support to replace the
battery.
Step 3 Connect the reserved battery cables.
Distinguish the positive and negative battery terminals when connecting battery
cables.
Issue 01 (2021-04-20)
NO TICE
NO TICE
Copyright © Huawei Technologies Co., Ltd.
8 Installing Devices Inside the Pre-fab. Module
91

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents