Huawei FusionDC1000A Commissioning Manual
Huawei FusionDC1000A Commissioning Manual

Huawei FusionDC1000A Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

Quick Links

FusionDC1000A Prefabricated All-in-One Data
Center
V100R021C00
Commissioning Guide (IT Scenario)
Issue
01
Date
2021-04-20
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei FusionDC1000A

  • Page 1 FusionDC1000A Prefabricated All-in-One Data Center V100R021C00 Commissioning Guide (IT Scenario) Issue Date 2021-04-20 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    About This Document About This Document Purpose This document describes how to power on and commission the FusionDC1000A prefabricated all-in-one data center solution (FusionDC1000 for short) in terms of safety precautions, preparations, power-on check, power-on commissioning, joint commissioning, power-off, and core device commissioning. It provides you a quick grasp of how to commission the prefabricated all-in-one data center.
  • Page 4 Change History Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues. Issue 01 (2021-04-20) This issue is the first official release. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    4.2.2 Powering Off Batteries..............................31 4.2.3 Performing EPO..................................31 4.2.4 Clearing the EPO State..............................32 4.3 Commissioning Smart Cooling Products........................32 4.4 Commissioning Monitoring Devices..........................34 4.4.1 Commissioning the Access Control System......................34 Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 6 5 System Commissioning......................54 5.1 Switching Between Two Power Supplies........................54 5.2 Fire Extinguishing System Commissioning (Standard).................... 55 5.3 Fire Extinguishing System Commissioning (CE)......................61 5.4 System Power-Off................................. 66 A Acronyms and Abbreviations..................... 68 Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 7: Safety Information

    The "NOTICE", "CAUTION", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
  • Page 8 ● Keep irrelevant people away from the equipment. Only operators are allowed to access the equipment. ● Use insulated tools or tools with insulated handles, as shown in the following figure. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 9 Do not change the structure or installation sequence of equipment without permission. ● Do not touch a running fan with your fingers, components, screws, tools, or boards before the fan is powered off or stops running. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 10: Personnel Requirements

    Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements ● Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations. ●...
  • Page 11 0°C. Handle cables with caution, especially at a low temperature. – Cables stored at subzero temperatures must be stored at room temperature for at least 24 hours before they are laid out. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 12: Installation Environment Requirements

    Install the equipment in an area far away from liquids. Do not install it under areas prone to condensation, such as under water pipes and air exhaust vents, or areas prone to water leakage, such as air conditioner vents, ventilation Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 13 Any violations must be promptly pointed out by the site manager or safety supervisor and the involved personnel should be prompted for correction. Personnel who fail to stop violations will be forbidden from working. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 14: Mechanical Safety

    Ensure that the wider end of the ladder is at the bottom, or protective measures have been taken at the bottom to prevent the ladder from sliding. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 15 D ANGER When removing a heavy or unstable component from a cabinet, be aware of unstable or heavy objects on the cabinet. ● Be cautious to avoid injury when moving heavy objects. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 16: Cooling System Safety

    ● When maintaining or replacing components, pay attention to high-pressure components (such as the compressor and refrigerant pipe) to prevent the refrigerant system from being cracked or exploded due to misoperations. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 17: Pre-Fab. Module Safety

    Do not smoke or use open flame inside a pre-fab. module. ● Before performing fire operations inside a pre-fab. module, obtain the customer's approval and the required work permit and fully evaluate risks. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 18: Battery Safety

    NO TICE To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ●...
  • Page 19 When moving or handling a battery whose electrolyte leaks, note that the leaking electrolyte may hurt human bodies. ● If the battery temperature exceeds 60°C, check for and promptly handle any leakage. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 20: Others

    UPS output voltage level or frequency. Doing so may affect the power supply to equipment. ● Exercise caution when setting battery parameters. Incorrect settings will affect the power supply and battery lifespan. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 21: Commissioning Guide Usage

    ● Operations marked as optional in chapters, sections, or procedures can be performed depending on the actual situation. Huawei assumes no liability for any loss caused by unauthorized changes to the initial configuration parameters. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Preparations For Power-On Commissioning

    3.1 Tools The following table lists the tools required for power-on commissioning. Table 3-1 Tools Tools Phillips screwdriver Flat-head screwdriver Utility knife Multimeter Electroprobe Network cable tester Cable tie Insulation tape Marker Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 23 ● This table may not list some tools required at specific sites. Onsite installation personnel and technical support personnel should prepare tools based on site requirements. ● Some dedicated tools and installation materials provided with the equipment may not be listed in this table. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 24: Reference Documentation

    FusionDC1000 With power distribution engineer qualifications Cooling system Familiar with the cooling system configurations and the operations for each core device in the FusionDC1000 With cooling engineer qualifications Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 25: Check Before Power-On

    FusionDC1000 systems Experienced in data center maintenance 3.4 Check Before Power-On Preparations Tools: multimeter, screwdriver, step ladder, insulation megohmmeter, pressure gauge Documents: solution drawings and parameters Skill requirement: power distribution engineer Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 26 Power Measure the insulation of the There is no electricity ibuti cable power cables using an leakage in the power insulation insulation megohmmeter. supply and distribution syst system. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 27 Frequency Use a multimeter to measure ● Frequency range for the the input frequency of the 50 Hz scenario: 49–51 Power PDB. ● Frequency range for the 60 Hz scenario: 59–61 Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 28 Smart Check the smart cooling All smart cooling product cooling product compressor. compressor pads are product removed. compresso r pads Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 29 Check the lighting device ● Devices are installed in ting installation and connection. positions shown in the syst installatio lighting device layout n and diagram. connectio ● Cables are correctly connected. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 30: Commissioning Core Devices

    CA UTION Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Switch on all SPD circuit breakers in the integrated UPS.
  • Page 31: Powering On And Starting The Ups

    Step 1 (Skip this step in the case of ATS input.) Turn on the MCCB. Step 2 Turn on the UPS input circuit breaker QF1. The UPS is powered by the mains and initialization begins. The LCD displays the Huawei logo and an initialization progress bar. ----End Issue 01 (2021-04-20)
  • Page 32: Starting The Inverter

    PWR indicator on the AC actuator lights up. Press down the lighting button to power on the light. Step 4 Turn on the smart cooling product circuit breaker on the integrated UPS to power on the smart cooling products. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 33: Commissioning The Smartli

    UPS cannot be the red indicator is steady on. cold started. The green indicator blinks at 1 Hz or is The UPS can be cold started. steady on (blinking at long intervals). Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 34 Then, power on slave cabinets one by one in the same way. Step 3 Set the language, time, date, network parameters, and system parameters on the Settings Wizard screen of the SmartLi. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 35 Mode 1 can meet the Mode 1 Mode 1, Mode 2 requirements of most customers. Mode 2 meets the requirements for charging batteries immediately after discharging is complete at a high temperature. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 36 Disable, Enable overcurrent Disable, no alarm is (discharge) reported when battery overcurrent occurs during discharging. If this parameter is set to Enable, an alarm is reported when battery overcurrent occurs during discharging. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Powering Off Batteries

    SmartLi cabinets one by one.) NO TICE If batteries are powered off and will not be charged for more than a month, remove the BCU. ----End 4.2.3 Performing EPO Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 38: Clearing The Epo State

    Step 3 View active alarms and ensure that the Battery cabinet shutdown alarm has disappeared from the alarm list. ----End 4.3 Commissioning Smart Cooling Products Prerequisites The power-on commissioning for the upstream PDF of air cooled precision smart cooling products is completed. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 39 Step 4 Tap Start on the main screen, and tap Confirm in the dialog box that appears. If the start succeeds, the system prompts that the command is successfully executed. ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Commissioning Monitoring Devices

    If the door of the pre-fab. module can be opened, the emergency door release button functions properly. ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 41: Commissioning Fire Extinguishing Devices (Standard)

    Step 2 Switch on the active and standby power supplies to power on the fire alarm control panel. Figure 4-3 Positions of power switches Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 42: Commissioning The Emergency Light (Standard)

    For the diagrams, see the initial configuration parameter manual for the solution in use. Procedure Step 1 Press the emergency light test button and check whether the emergency light enters the working mode. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 43: Commissioning Fire Extinguishing Devices (Ce)

    Documents: drawings and parameters for power supply and distribution as well as fire extinguishing Skill requirement: fire engineer Procedure Step 1 Turn off the upstream switch for the emergency light power cable. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 44 The emergency light turns off, and the power indicator turns on. Step 6 Press the red button of the emergency light. The emergency light turns on. When you release the red button, the emergency light turns off. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 45: Optional) Commissioning The Asd

    Press the Set/Res button to start the reset. Wait until the two airflow LEDs in the middle turn on. Rotate the knob switch Mode to position 1. Press the Set/Res button to finish the reset. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 46: Optional) Neteco Management

    (protected by a security mechanism) on the ECC800-Pro. Table 4-5 Default IP addresses for the WAN and LAN ports on the ECC800-Pro Port Default IP Address WAN1 192.168.8.10 WAN2 192.168.0.10 192.168.248.10 (FusionModule800) LAN1 and LAN2 192.168.248.10 Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 47 Compatibility View, and add the web access address to the compatibility view. Choose Tools > Internet options > Security, choose Add the ECC800-Pro IP address to the list of trusted sites. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 48 Step 5 Log in to the ECC800-Pro WebUI. Enter https://monitoring IP address (such as monitoring IP address https:// 192.168.8.10) in the address box of the browser, and then press Enter to enter the WebUI login page. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 49: Performing Basic Operations Before Adding Devices

    – After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 50: Ip Address Preinstallation Planning

    The IP address must be unique on the live network. ● You can plan only one IP address for one network interface. It is not allowed to plan or set multiple IP addresses for the same network interface. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 51: Obtaining The Neteco Software License

    4.7.2.2 Obtaining the NetEco Software License The NetEco software license is not provided together with software to the customer. Therefore, obtain the NetEco software license in advance. Obtain the license from the Huawei's enterprise support website. ● For enterprise users: Log in to Huawei's enterprise support website https:// support.huawei.com/enterprise.
  • Page 52: Loading The Neteco Software License

    Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 53: Creating A Management Domain

    NE types and versions in Mapping Table . ● For carriers: Log in to Huawei's carrier support website https://support.huawei.com. Obtain iManager NetEco 6000 V600R021C00SPCXXX ReleaseDoc_ENG.zip, NetEco6000_V600R021C00SPCXXX_Adapters.zip, and NetEco6000_V600R021C00SPCXXX_DomainAdapters.zip from Support > Product Support > Carrier Cloud & Data Center > Data Center Facility >...
  • Page 54: How Can I Set And Add A Smartli (Modbus-Tcp)

    Step 1 Set SmartLi monitoring parameters. On the home screen of the SmartLi, tap System Info. Choose System Info > Settings, enter the user name admin and password 000001, and tap Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 55: Process Of Adding A Device

    Prerequisites ● You have logged in to the NetEco client using a web browser. ● You have the operation rights for Data Center Planning. Interface Introduction Figure 4-12 Adding a device Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 56: Setting And Adding The Ecc800 Collector

    Settings > address assigned by the network System administrator. Parameter Subnet 255.255.25 Set this parameter based on the s > mask subnet mask assigned by the network Monitor IP administrator. > WAN_1 Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 57 $'(8-32 characters that include at least three of the following types: lowercase Authenticati letters, uppercase letters, digits, and on Password special characters) Confirm authenticatio n password Step 5 Click Submit. ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 58: Setting The Transparent Transmission Function For The Ecc800-Pro Collector

    Step 7 (Optional) If the management domain is a rack, click the management domain and choose Design under . The page for adding a device is displayed. Otherwise, skip this step. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 59 If Connection mode is set to Security protocol, enter the value of Confirm password that has been set on the ECC800-Pro WebUI, and click Confirm. Figure 4-13 Page for managing transparent transmission channels ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 60: System Commissioning

    Step 9 Check whether the power supply to the downstream devices is normal. NO TE During the operation, if the power supply to the downstream devices is normal, the switchover between the two power supplies is successful. ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 61: Fire Extinguishing System Commissioning (Standard)

    Step 2 Press # to switch the mode. When 324 is displayed on the screen, use a dedicated external connection cable to connect the terminal device and set the address code for the device on the bus. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 62 Step 8 Press Keyboard and enter the password (the initial password is 111111) to unlock the keyboard. Then press Auto/Manual to set the fire alarm control panel to the Auto mode. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 63 Figure 5-2 Measuring the voltage between the two terminals of the electromagnetic valve Step 12 Commission the pressure announciator. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 64 ● Open the protective cover on the emergency start/abort button panel, and operate the start and abort buttons, as shown in Figure 5-4. ● Reset the START and STOP buttons after the commissioning (the buttons bounce up). Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 65 Hold the smoke detector body, align the smoke detector indicator with the position shown by (1) in Figure 5-6, and turn the detector body clockwise to the position shown by (2) in Figure 5-6 to install the smoke detector. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 66 Step 15 Press Reset to reset the fire alarm control panel. Step 16 (Optional) Check whether the fire alarm signals are reported to the management system. Step 17 Reconnect cables to the electromagnetic valve. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Fire Extinguishing System Commissioning (Ce)

    Remove the safety pin. Figure 5-9 Removing the safety pin ----End 5.3 Fire Extinguishing System Commissioning (CE) Prerequisites ● The extinguishant control panel has been powered on. ● The management system is working properly. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 68 Step 3 Flip the key leftward to Auto & Manual, and set the extinguishant control panel to Auto & Manual. Figure 5-10 Auto & Manual indicator position Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 69 The horn strobe is triggered, and the warning sign blinks. The Release Imminent indicator on the extinguishant control panel turns on, and the release countdown starts. When the countdown ends, the ejector of the electrical actuator pops up. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 70 EEE to Ad, press Reset on the extinguishant control panel to reset the extinguishant control panel. Figure 5-13 Enable Control position Step 9 Commission the pneumatic switch. Open the cover of the pneumatic switch. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 71 – The extinguishant control panel generates a LOCAL FIRE alarm, and Extinguishant Release indicator turns on. The warning sign is steady on. – LOCAL FIRE terminal generates a LOCAL FIRE alarm signal. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 72: System Power-Off

    Step 10 (Optional) Check whether the fire alarm signals are reported to the management system. Step 11 Reinstall the electrical actuator on the container valve. ----End 5.4 System Power-Off Prerequisites The FusionDC1000 is powered on, commissioned, and working properly. Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 73 Switch off the circuit breakers from the end to start of the power supply and distribution system to power off devices. For details, see the power supply and distribution system diagram. Switch off the external input power circuit breaker for the FusionDC1000. ----End Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.
  • Page 74: A Acronyms And Abbreviations

    Commissioning Guide (IT Scenario) A Acronyms and Abbreviations Acronyms and Abbreviations aspirating smoke detector automatic transfer switch Conformite Europende power distribution frame power distribution unit rPDU rack power distribution unit uninterruptible power system Issue 01 (2021-04-20) Copyright © Huawei Technologies Co., Ltd.