Procedure
Step 1 Remove the bolts from the sliding door fasteners using an adjustable wrench, and
remove the sliding door fasteners.
Figure 7-9 Removing the sliding door fasteners
Step 2 Remove the piston rings, and install them in the screw holes in the floor under the
sliding door and the beam above the sliding door.
----End
Follow-up Procedure
When a pre-fab. module needs to be relocated, refer to the preceding steps to
adjust the sliding door fasteners in reverse order to secure the sliding doors.
Issue 01 (2021-04-20)
NO TE
The plugs are packed and secured above the door handle before delivery.
Copyright © Huawei Technologies Co., Ltd.
7 Removing Transport Protection Materials
67

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents