Huawei FusionDC1000A Installation Manual page 106

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Table 9-1 Generator start/stop cable connection
Cable Connecting Position in the Device
Generator start/stop
Figure 9-3 Connecting the generator start/stop cables for the UPS
(1) XT2 terminal block
----End
Issue 01 (2021-04-20)
NO TE
Here connecting one of the cables is used as an example. XT2-6 is a normally open contact,
XT2-7 is a common contact, and XT2-8 is a normally closed contact.
Copyright © Huawei Technologies Co., Ltd.
9 Installing Cables Outside the Pre-fab. Module
Generator Start
Generator Com
Generator Stop
Cable Connecting
Position in the UPS
XT2-6
XT2-7
XT2-8