Laying Out Cables - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Procedure
Step 1 Select a cable to be connected between two devices. Measure the cable route
length between the two devices using a thin rope or small cable (such as a signal
cable or fire control cable) available on-site.
Step 2 Add the length reserved for installing terminals and a tolerance to the cable
length measured in
----End
A.1.3 Laying Out Cables
Prerequisites
Some external cables for the FusionDC1000 are long and thick. Assign at least two
persons to lay out cables especially armored cables if no assistant tool is available
onsite.
Preparations
Tools: protective gloves and marker
Material: cable
Skill requirement: common technician
Procedure
Step 1 Select the designed cables.
Step 2 Lay out cables to the required run length.
To protect cable sheathings, do not press or stab cables with a hard object and do
not drag cables on the ground at will during cable layout.
Issue 01 (2021-04-20)
Step 1
NO TE
● To improve installation efficiency, complete all cable measurements before you perform
subsequent operations.
● Determine the length of the other cables between the devices based on the length of
the cable measured.
● To facilitate installation, it is recommended that you lay out cables to the measured
cable route length plus about 2 m.
Do not lay out cables outdoors under bad weather conditions if no shelter is
available.
Cables have been measured.
NO TICE
NO TICE
Copyright © Huawei Technologies Co., Ltd.
to determine the required cable run length.
A Basic Installation Operations
107