Optional) Installing Awnings - Huawei FusionDC1000A Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 5-2 Installing the external cable tray
----End

5.2 (Optional) Installing Awnings

Context
An awning must be installed on the top of the main entrance door to prevent
rainwater from entering the pre-fab. module when the door is open.
Preparations
Tools: socket wrench, Phillips screwdriver, glue gun, step ladder
Materials: awning, awning mounting plate, rubber pad, white sealant, awning
bolt, washer
Skill requirement: common technician
Procedure
Step 1 Secure the awning mounting plate at the top of the pre-fab. module door.
Issue 01 (2021-04-20)
Copyright © Huawei Technologies Co., Ltd.
5 Installing External Accessories for the Pre-fab.
Module
50

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents