Figure A-11 Routing a cable
Step 3 Wrap four circles of waterproof sealing tape around the joint between the cable
and the waterproof metal connector.
Figure A-12 Wrapping sealing tape
If the cable is not regular or the size does not meet the requirements, wrap waterproof sealing
tape.
Step 4 Secure the waterproof metal connector using the dedicated feeder window wrench
by tightening the nut to a torque of 100 N·m.
Figure A-13 Securing the waterproof metal connector
Step 5 Apply transparent sealant onto the joint between the waterproof metal connector
and the sheet metal on the pre-fab. module.
Issue 01 (2021-04-20)
NO TE
Copyright © Huawei Technologies Co., Ltd.
A Basic Installation Operations
115

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents